题目
下图是某项目 8 个月的累计计划价值(PV)、挣值(EV)与实际成本(AC)曲线,状态日期为第 6 个月末。截至状态日期,项目处于什么状态?
The chart shows cumulative planned value (PV), earned value (EV) and actual cost (AC) for a project over eight months; the status date is the end of month 6. What is the project's status at the status date?

选项
- A.Ahead of schedule and over budget
- B.Behind schedule and under budget
- C.Behind schedule and over budget
- D.Ahead of schedule and under budget
解析
解析:第 6 个月末:EV 为 620、PV 为 700,SPI = 620 ÷ 700 小于 1,说明进度落后;AC 为 540、低于 EV 620,CPI = 620 ÷ 540 大于 1,说明已完成工作的花费低于计划,成本有节约。两条线一上一下,对应“进度落后、成本低于预算”。
Rationale:At month 6 the EV curve (620) lies below PV (700), so SPI = 620/700 < 1 and the project is behind schedule. AC (540) lies below EV (620), so CPI = 620/540 > 1 and the work done cost less than planned.