题目
某项目的 CPI 为 0.85,SPI 为 1.1。项目经理应如何解读这些结果?
A project's CPI is 0.85, and SPI is 1.1. How should the project manager interpret these results?
选项
- A.The project is under budget and behind schedule
- B.The project is over budget and ahead of schedule
- C.The project is under budget and ahead of schedule
- D.The project is over budget and behind schedule
解析
解析:CPI 低于 1.0 表示实际花费高于计划(成本超支);SPI 高于 1.0 表示工作进展快于计划(进度超前)。
Rationale:A CPI below 1.0 indicates the project is spending more than planned (over budget). An SPI above 1.0 means work is progressing faster than planned, so the project is ahead of schedule.