题目
下图是某项目的活动网络图,方框内标注活动与工期(天),箭头表示完成—开始依赖关系。
活动 B 的总时差是多少天?
The diagram shows the activity network for a project; each box gives the activity and its duration in days, and arrows are finish-to-start dependencies.
What is the total float of activity B?

选项
- A.0 days
- B.2 days
- C.4 days
- D.6 days
解析
解析:从起点到终点有两条路径:A-B-D-F 合计 3+4+2+3 = 12 天,E-C-D-F 合计 6+5+2+3 = 16 天,关键路径为 16 天,因此 D 最晚必须在第 11 天开始。B 在第 3 天开始、工期 4 天,其最晚开始时间为 11 − 4 = 7,总时差 = 7 − 3 = 4 天。
Rationale:Two paths run from start to finish: A-B-D-F = 3+4+2+3 = 12 and E-C-D-F = 6+5+2+3 = 16, so the critical path is 16 days and D must start no later than day 11. B starts at day 3 and takes 4 days; its latest start is 11 - 4 = 7, so total float is 7 - 3 = 4 days.