挣值分析:偏差判读 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-170

题目

你的项目数据如下:计划价值 450,000;挣值 400,000;实际成本 500,000。项目处于什么状态?
Your project shows these figures: planned value 450,000; earned value 400,000; actual cost 500,000. What is the status?

选项

  1. A.Under budget and ahead of schedule.
  2. B.Over budget and behind schedule.
  3. C.Over budget and ahead of schedule.
  4. D.Under budget and behind schedule.
正确答案:B

解析

解析:CPI = EV / AC = 400,000 / 500,000 = 0.8,说明花得比挣得多,即超预算。SPI = EV / PV = 400,000 / 450,000 ≈ 0.89,说明进度落后。任何指数低于 1 都是不利的。 Rationale:CPI = EV / AC = 400,000 / 500,000 = 0.8, so you are spending more than you earn (over budget). SPI = EV / PV = 400,000 / 450,000 ≈ 0.89, so you are behind schedule. Any index below 1 is unfavourable.

同考点练习题