题目
你的项目数据如下:计划价值 450,000;挣值 400,000;实际成本 500,000。项目处于什么状态?
Your project shows these figures: planned value 450,000; earned value 400,000; actual cost 500,000. What is the status?
选项
- A.Under budget and ahead of schedule.
- B.Over budget and behind schedule.
- C.Over budget and ahead of schedule.
- D.Under budget and behind schedule.
解析
解析:CPI = EV / AC = 400,000 / 500,000 = 0.8,说明花得比挣得多,即超预算。SPI = EV / PV = 400,000 / 450,000 ≈ 0.89,说明进度落后。任何指数低于 1 都是不利的。
Rationale:CPI = EV / AC = 400,000 / 500,000 = 0.8, so you are spending more than you earn (over budget). SPI = EV / PV = 400,000 / 450,000 ≈ 0.89, so you are behind schedule. Any index below 1 is unfavourable.