项目团队把验收测试中发现的缺陷按类别统计,并绘制了带累计百分比的帕累托图(见下图)。质量改进工作应优先聚焦在哪里?
The project team charted the defects found in acceptance testing by category, together with the cumulative percentage (see the chart). Where should the quality improvement effort focus first?

选项
- A.The first two categories (A and B), which together account for about 80% of the defects
- B.All five categories equally, to keep the effort balanced
- C.Category E, because it has the fewest defects and is quickest to fix
- D.No category in particular; wait for more test data before acting
解析
解析:帕累托图按发生频次排序,用来定位“关键的少数”。图中 A 占 52%、B 占 28%,两者累计约 80%,先把这两类缺陷解决掉,就能以最小投入消除绝大部分缺陷量;平均投入或只挑最容易的一类都不符合帕累托原则。
Rationale:A Pareto chart ranks causes by frequency and shows where the "vital few" lie: A (52%) and B (28%) together reach roughly 80% of all defects. Fixing those two categories removes most of the defect volume with the least effort.