题目
请查看状态表(单位:千美元):设计 PV 50 / EV 50 / AC 45;建设 PV 120 / EV 100 / AC 90;测试 PV 40 / EV 44 / AC 50;部署 PV 30 / EV 24 / AC 32。哪个工作流进度落后但成本节约?
Review the status table (values in thousands of dollars): Design PV 50 / EV 50 / AC 45; Build PV 120 / EV 100 / AC 90; Test PV 40 / EV 44 / AC 50; Deploy PV 30 / EV 24 / AC 32. Which workstream is behind schedule but under budget?
选项
- A.Design
- B.Build
- C.Test
- D.Deploy
解析
解析:进度偏差 SV = EV − PV,成本偏差 CV = EV − AC。建设流 SV 为 −20(落后),CV 为 +10(低于预算)。设计按计划,测试超前但超支,部署既落后又超支。
Rationale:Schedule variance is EV minus PV, and cost variance is EV minus AC. Build has SV of minus 20 (behind) and CV of plus 10 (under budget). Design is on schedule, Test is ahead but over budget, and Deploy is behind and over budget.