题目
某项目 PV = 30 万美元,EV = 27 万美元,AC = 31 万美元。这说明项目处于什么状态?
A project has PV = $300,000, EV = $270,000, AC = $310,000. What does this tell you about the project?
选项
- A.The project is ahead of schedule and over budget.
- B.The project is ahead of schedule and under budget.
- C.The project is behind schedule and under budget.
- D.The project is behind schedule and over budget.
解析
解析:D 正确。SV = EV − PV = 27 − 30 = −3 万美元(负值表示进度落后);CV = EV − AC = 27 − 31 = −4 万美元(负值表示成本超支);CPI = 27/31 ≈ 0.87(小于 1 即超支);SPI = 27/30 = 0.90(小于 1 即落后)。两项指标均不利,需要立即纠正。
Rationale:D is correct. SV = EV − PV = $270K − $300K = −$30K (negative = behind schedule). CV = EV − AC = $270K − $310K = −$40K (negative = over budget). CPI = 270/310 = 0.87 (below 1.0 = over budget). SPI = 270/300 = 0.90 (below 1.0 = behind schedule). Both indicators are unfavourable, the project needs immediate corrective action.