挣值分析:偏差判读 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-291

题目

某项目 PV = 30 万美元,EV = 27 万美元,AC = 31 万美元。这说明项目处于什么状态?
A project has PV = $300,000, EV = $270,000, AC = $310,000. What does this tell you about the project?

选项

  1. A.The project is ahead of schedule and over budget.
  2. B.The project is ahead of schedule and under budget.
  3. C.The project is behind schedule and under budget.
  4. D.The project is behind schedule and over budget.
正确答案:D

解析

解析:D 正确。SV = EV − PV = 27 − 30 = −3 万美元(负值表示进度落后);CV = EV − AC = 27 − 31 = −4 万美元(负值表示成本超支);CPI = 27/31 ≈ 0.87(小于 1 即超支);SPI = 27/30 = 0.90(小于 1 即落后)。两项指标均不利,需要立即纠正。 Rationale:D is correct. SV = EV − PV = $270K − $300K = −$30K (negative = behind schedule). CV = EV − AC = $270K − $310K = −$40K (negative = over budget). CPI = 270/310 = 0.87 (below 1.0 = over budget). SPI = 270/300 = 0.90 (below 1.0 = behind schedule). Both indicators are unfavourable, the project needs immediate corrective action.