挣值分析:偏差判读 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-256

题目

某项目 BAC 为 50 万美元。在状态日期,PV = 20 万美元,EV = 16 万美元,AC = 18 万美元。假设当前成本绩效持续,完工估算(EAC)是多少?
A project has a BAC of $500,000. At the status date, PV = $200,000, EV = $160,000, and AC = $180,000. What is the Estimate at Completion (EAC) assuming current cost performance continues?

选项

  1. A.$562,500
  2. B.$520,000
  3. C.$540,000
  4. D.$480,000
正确答案:A

解析

解析:A 正确。EAC = BAC ÷ CPI。CPI = EV ÷ AC = 160,000 ÷ 180,000 ≈ 0.889;EAC = 500,000 ÷ 0.889 ≈ 562,500。该公式假设当前成本绩效延续到剩余工作。项目同时超预算(CPI<1)且落后进度(SV = EV − PV = −40,000),需要采取纠正措施。 Rationale:A is correct. EAC = BAC ÷ CPI. CPI = EV ÷ AC = $160,000 ÷ $180,000 = 0.889. EAC = $500,000 ÷ 0.889 = $562,500 (rounded). This formula assumes current cost performance (CPI) will continue for the remaining work. The project is both over budget (CPI < 1) and behind schedule (SV = EV − PV = -$40,000), signalling the need for corrective action.