题目
某项目 BAC 为 50 万美元。在状态日期,PV = 20 万美元,EV = 16 万美元,AC = 18 万美元。假设当前成本绩效持续,完工估算(EAC)是多少?
A project has a BAC of $500,000. At the status date, PV = $200,000, EV = $160,000, and AC = $180,000. What is the Estimate at Completion (EAC) assuming current cost performance continues?
选项
- A.$562,500
- B.$520,000
- C.$540,000
- D.$480,000
解析
解析:A 正确。EAC = BAC ÷ CPI。CPI = EV ÷ AC = 160,000 ÷ 180,000 ≈ 0.889;EAC = 500,000 ÷ 0.889 ≈ 562,500。该公式假设当前成本绩效延续到剩余工作。项目同时超预算(CPI<1)且落后进度(SV = EV − PV = −40,000),需要采取纠正措施。
Rationale:A is correct. EAC = BAC ÷ CPI. CPI = EV ÷ AC = $160,000 ÷ $180,000 = 0.889. EAC = $500,000 ÷ 0.889 = $562,500 (rounded). This formula assumes current cost performance (CPI) will continue for the remaining work. The project is both over budget (CPI < 1) and behind schedule (SV = EV − PV = -$40,000), signalling the need for corrective action.
同考点练习题
-
PMP202611-022 · 答案 B
-
PMP202611-046 · 答案 B
-
PMP202611-120 · 答案 A
-
PMP202611-170 · 答案 B
-
PMP202611-291 · 答案 D
-
PMP202611-359 · 答案 B
-
PMP202611-396 · 答案 C
-
PMP202611-436 · 答案 C