题目
某项目第 6 个月挣值数据为:计划价值 PV = 50 万美元,挣值 EV = 42 万美元,实际成本 AC = 48 万美元。成本绩效指数(CPI)是多少?它说明项目处于什么状态?
A project has the following earned value metrics at month 6: Planned Value (PV) = $500,000, Earned Value (EV) = $420,000, Actual Cost (AC) = $480,000. What is the Cost Performance Index (CPI), and what does it indicate about the project?
选项
- A.CPI = 0.875; the project is over budget, and each dollar spent produces only $0.88 of planned value
- B.CPI = 1.14; the project is under budget and performing well financially
- C.CPI = 0.84; the project is behind schedule
- D.CPI = 1.05; the project is slightly over budget but within an acceptable range
解析
解析:CPI = EV / AC = 42 万 / 48 万 = 0.875。CPI 小于 1 表示超预算:每花 1 美元仅获得约 0.875 美元的计划价值。(SPI = EV / PV = 0.84 说明进度也落后,但本题问的是 CPI。)
Rationale:CPI = EV / AC = 420,000 / 480,000 = 0.875. A CPI below 1.0 means the project is over budget: each dollar spent yields only about $0.875 of planned value. (SPI = EV / PV = 0.84 indicates the project is also behind schedule, but the question asks about CPI.)