题目
项目经理收到月度财务报告:预算 50 万美元中已花 45 万,工作完成 60%。现状如何,项目经理该怎么做?
A project manager receives the monthly financial report showing the project has spent $450,000 of a $500,000 budget with 60% of work complete. What is the situation and what should the PM do?
选项
- A.Continue monitoring, the remaining 40% may be cheaper than the first 60%.
- B.The project is in trouble: CPI = EV/AC = 0.67, meaning only $0.67 of value is delivered per $1 spent. At this rate, EAC = $500,000 ÷ 0.67 = ~$747,000. The PM should immediately investigate root causes, develop recovery options and brief the sponsor.
- C.Request a budget increase of $50,000 to cover the remaining 40% of work.
- D.The project is on track: 90% of budget used with 60% complete seems reasonable.
解析
解析:B 正确。EV = 60% × 500,000 = 300,000;AC = 450,000;CPI = 300,000 ÷ 450,000 = 0.67;EAC = 500,000 ÷ 0.67 ≈ 747,000。按此预测将超支近 25 万美元,属严重状况,必须立即行动。“看起来合理”(D)无视挣值计算;追加 5 万(C)相对预测严重不足;被动监控(A)无视明确的预警信号。
Rationale:B is correct. EV = 60% × $500,000 = $300,000. AC = $450,000. CPI = $300,000 ÷ $450,000 = 0.67. EAC = BAC ÷ CPI = $500,000 ÷ 0.67 = ~$747,000. The project is projected to cost nearly $250,000 over budget, a critical situation requiring immediate action. "Seems reasonable" (D) ignores the EVM calculation. A $50,000 request (C) is wildly insufficient given the forecast. Passive monitoring (A) ignores the clear warning signal.