挣值分析:偏差判读 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-396

题目

项目经理审阅挣值报告:SPI 为 1.15,CPI 为 0.88。对项目状态最准确的描述是什么?
A project manager is reviewing an earned value report. The project has a SPI of 1.15 and a CPI of 0.88. What is the most accurate description of the project's status?

选项

  1. A.Ahead of schedule and under budget.
  2. B.Behind schedule and over budget.
  3. C.Ahead of schedule but over budget, the team is moving fast but spending more than planned per unit of work.
  4. D.Behind schedule and under budget.
正确答案:C

解析

解析:C 正确。SPI = 1.15 大于 1,表示进度提前(完成的工作多于计划);CPI = 0.88 小于 1,表示超预算(每获得 1 美元计划价值要花超过 1 美元)。这种组合常见于靠加人或加班赶工的项目——两者都会推高成本。项目经理应查明:加速带来的进度收益是否值这笔超支,还是存在效率问题。 Rationale:C is correct. SPI = 1.15 > 1.0 means ahead of schedule (more work completed than planned). CPI = 0.88 < 1.0 means over budget (spending more than $1 for every $1 of planned value). This combination is common when teams accelerate by adding resources or overtime: both of which increase cost. The project manager should investigate whether the schedule acceleration justifies the cost overrun or whether inefficiency is the cause.

同考点练习题