项目经理审阅挣值报告:SPI 为 1.15,CPI 为 0.88。对项目状态最准确的描述是什么?
A project manager is reviewing an earned value report. The project has a SPI of 1.15 and a CPI of 0.88. What is the most accurate description of the project's status?
选项
- A.Ahead of schedule and under budget.
- B.Behind schedule and over budget.
- C.Ahead of schedule but over budget, the team is moving fast but spending more than planned per unit of work.
- D.Behind schedule and under budget.
解析
解析:C 正确。SPI = 1.15 大于 1,表示进度提前(完成的工作多于计划);CPI = 0.88 小于 1,表示超预算(每获得 1 美元计划价值要花超过 1 美元)。这种组合常见于靠加人或加班赶工的项目——两者都会推高成本。项目经理应查明:加速带来的进度收益是否值这笔超支,还是存在效率问题。
Rationale:C is correct. SPI = 1.15 > 1.0 means ahead of schedule (more work completed than planned). CPI = 0.88 < 1.0 means over budget (spending more than $1 for every $1 of planned value). This combination is common when teams accelerate by adding resources or overtime: both of which increase cost. The project manager should investigate whether the schedule acceleration justifies the cost overrun or whether inefficiency is the cause.