关键路径与浮动时间 · PMP 练习题解析

进度管理 困难 Process 过程域 题号 PMP202611-664

题目

下表列出若干项目活动的工期与前置活动。 关键路径的工期是多少?
The table below is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?
下表列出若干项目活动的工期与前置活动。 关键路径的工期是多少?

选项

  1. A.11
  2. B.14
  3. C.9
  4. D.13
正确答案:B

解析

解析:把所有路径列出来并累加工期:A-C-D = 2+6+3 = 11;A-B-D = 2+4+3 = 9;E-B-D = 7+4+3 = 14;E-F = 7+2 = 9。最长的一条是 Start-E-B-D-End,因此关键路径工期为 14。 Rationale:Enumerate every path: A-C-D = 2+6+3 = 11; A-B-D = 2+4+3 = 9; E-B-D = 7+4+3 = 14; E-F = 7+2 = 9. The longest path, Start-E-B-D-End, gives a critical path duration of 14.