关键路径与浮动时间 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-048

题目

你在计算关键路径。活动 A(5 天)先于活动 B(3 天)。若活动 A 延误 2 天且浮动时间为零,会发生什么?
You are calculating the Critical Path. Activity A (5 days) precedes Activity B (3 days). If Activity A is delayed by 2 days and has zero float, what happens?

选项

  1. A.The project end date remains unchanged
  2. B.The project is delayed by 2 days
  3. C.The project is delayed by 5 days
  4. D.Activity B gains additional float
正确答案:B

解析

解析:关键路径上的活动总浮动为零,任何延误都会直接导致整个项目工期推迟。 Rationale:Activities on the critical path have zero float, meaning any delay directly delays the entire project timeline.