题目
你在计算关键路径。活动 A(5 天)先于活动 B(3 天)。若活动 A 延误 2 天且浮动时间为零,会发生什么?
You are calculating the Critical Path. Activity A (5 days) precedes Activity B (3 days). If Activity A is delayed by 2 days and has zero float, what happens?
选项
- A.The project end date remains unchanged
- B.The project is delayed by 2 days
- C.The project is delayed by 5 days
- D.Activity B gains additional float
解析
解析:关键路径上的活动总浮动为零,任何延误都会直接导致整个项目工期推迟。
Rationale:Activities on the critical path have zero float, meaning any delay directly delays the entire project timeline.