关键路径与浮动时间 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-306

题目

某项目有三条路径:A 路径 10 周,B 路径 12 周,C 路径 9 周,其中 C 路径有 2 周浮动时间。关键路径工期是多少?
A project has three potential paths: Path A (10 weeks), Path B (12 weeks), Path C (9 weeks). Path C has 2 weeks of float. What is the critical path duration?

选项

  1. A.9 weeks: Path C is the shortest.
  2. B.12 weeks: Path B is the longest path with zero float.
  3. C.10 weeks: Path A is the longest path.
  4. D.11 weeks: the average of all three paths.
正确答案:B

解析

解析:B 正确。关键路径是网络中最长的路径、浮动为零,决定项目最短工期。B 路径 12 周最长,即关键路径。A 路径浮动为 2 周(12−10),C 路径浮动为 3 周(12−9)。项目工期为 12 周,B 路径上任一活动延误都会拖累整个项目。 Rationale:B is correct. The critical path is the longest path through the network and has zero float; it determines the minimum project duration. Path B at 12 weeks is the longest, so it is the critical path. Path A has 2 weeks of float (12 − 10), and Path C has 3 weeks of float (12 − 9). The project duration is therefore 12 weeks, and any delay on Path B activities delays the whole project.