关键路径与浮动时间 · PMP 练习题解析

进度管理 困难 Process 过程域 题号 PMP202611-264

题目

项目执行期间,供应商通知项目经理:由于供应链问题,一个关键部件将延迟 3 周交付。该部件位于关键路径上。项目经理首先应该怎么做?
During project execution, a vendor informs the project manager that a key component will be delivered 3 weeks late due to supply chain issues. This component is on the critical path. What should the project manager do first?

选项

  1. A.Evaluate the schedule impact, identify options (alternative suppliers, fast-tracking, crashing) and prepare a recommended recovery plan before escalating.
  2. B.Update the risk register and continue with other project activities.
  3. C.Immediately inform the sponsor that the project will be delayed by 3 weeks.
  4. D.Issue a formal claim against the vendor for the delay and any associated costs.
正确答案:A

解析

解析:A 正确。项目经理的价值在于解决问题,而不只是把问题上交。先分析全面影响并准备恢复方案,才能给发起人可执行的信息,而不是只报坏消息。未分析就升级(C)属过早;正式索赔(D)或许后续合适,但不是第一步;只更新登记册(B)而不行动,等于无视关键路径延误。 Rationale:A is correct. The project manager's value is in problem-solving, not just escalating problems. Analysing the full impact and preparing recovery options before escalating gives the sponsor actionable information rather than just bad news. Immediate escalation (C) is premature before analysis. A formal claim (D) may be appropriate later but not as the first step. Updating the register (B) without action ignores a critical path delay.