题目
项目管理计划规定采用预测型开发方式来产出项目交付物。
在项目生命周期中,整体项目风险最低出现在哪个位置?
(真实考试中需在图上点选区域,本题请选择对应标号。)
The project management plan specifies that a predictive development approach has been selected to produce the project deliverables.
Where in the project life cycle will the overall project risk be the lowest?
(On the real exam you would click the correct area of the image; here select the matching label.)

选项
- A.A(starting the project)
- B.B(organizing and preparing)
- C.C(carrying out the work)
- D.D(closing the project)
解析
解析:整体项目风险在项目起步时最高:目标尚在定义、交付物还没产出;随着决策做出、交付物被验收、目标逐步达成,风险持续下降。到收尾阶段未知因素最少,即图中区域 D,风险最低。
Rationale:Overall project risk is highest at the start, when objectives are still being defined and nothing has been delivered, and falls as decisions are made, deliverables are accepted and objectives are met. It is lowest during closing, area D.