关键路径与浮动时间 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-060

题目

项目关键路径原为 15 周。对活动赶工后工期变为 13 周。新的关键路径是多长?
The project's critical path is 15 weeks. After crashing activities, the duration becomes 13 weeks. What is the new critical path?

选项

  1. A.15 weeks
  2. B.13 weeks
  3. C.14 weeks
  4. D.Cannot be determined
正确答案:B

解析

解析:赶工缩短了关键活动的持续时间,从而缩短了整个关键路径的长度。 Rationale:Crashing shortens the duration of critical activities, which reduces the overall critical path length.