题目
项目关键路径原为 15 周。对活动赶工后工期变为 13 周。新的关键路径是多长?
The project's critical path is 15 weeks. After crashing activities, the duration becomes 13 weeks. What is the new critical path?
选项
- A.15 weeks
- B.13 weeks
- C.14 weeks
- D.Cannot be determined
解析
解析:赶工缩短了关键活动的持续时间,从而缩短了整个关键路径的长度。
Rationale:Crashing shortens the duration of critical activities, which reduces the overall critical path length.