题目
项目进度中的关键路径是:
The critical path in a project schedule is:
选项
- A.The shortest path through the network
- B.The path with the most resources
- C.The path the sponsor prefers
- D.The longest path, determining the minimum project duration
解析
解析:关键路径是历时最长的路径,其上任何延误都会拖后整个项目。
Rationale:The critical path is the longest duration path; any delay on it delays the project.