题目

项目进度中的关键路径是:
The critical path in a project schedule is:

选项

  1. A.The shortest path through the network
  2. B.The path with the most resources
  3. C.The path the sponsor prefers
  4. D.The longest path, determining the minimum project duration
正确答案:D

解析

解析:关键路径是历时最长的路径,其上任何延误都会拖后整个项目。 Rationale:The critical path is the longest duration path; any delay on it delays the project.