题目
下图是某软件升级项目的进度甘特图。系统分析已于 8 月 12 日完成,截至 10 月 3 日系统设计与开发仍在进行。产品开发完成后还需测试与部署,且必须在 10 月 17 日前完成。挣值按完成百分比法计算。
截至 10 月 3 日,成本偏差是多少?
The Gantt chart below shows the schedule for a software upgrade project. System analysis was completed on August 12, but system design and development are still in progress as of October 3. Once the product is developed, the team must test and deploy it, and this must be completed by October 17. Earned value is determined based on percent complete.
What is the cost variance as of October 3?

选项
- A.($650)
- B.$3,750
- C.$650
- D.$3,100
解析
解析:成本偏差 = 挣值 − 实际成本。按图中数据:EV = 500×100% + 1000×75% + 5000×50% = 3,750 美元;AC = 600 + 500 + 2000 = 3,100 美元;CV = 3,750 − 3,100 = 650 美元。结果为正值,说明实际成本低于计划成本(成本节约)。
Rationale:CV = EV - AC. EV = 100% x $500 + 75% x $1,000 + 50% x $5,000 = $3,750. AC = $600 + $500 + $2,000 = $3,100. CV = $3,750 - $3,100 = $650, a positive value meaning the project is under planned cost.