关键路径与浮动时间 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-476

题目

关键链法与关键路径法的主要区别在于:
The critical chain method differs from critical path mainly by:

选项

  1. A.Explicitly accounting for resource constraints and buffers
  2. B.Ignoring resources
  3. C.Being faster to calculate
  4. D.Working only in agile
正确答案:A

解析

解析:关键链在关键路径基础上加入资源平衡与项目缓冲、接驳缓冲、资源缓冲。 Rationale:Critical chain adds resource leveling and buffers (project/feeding/resource) to the critical path concept.