项目经理计算某任务自由浮动:任务 A 工期 5 天,有两个紧后任务——B(FS,无滞后)最早开始第 8 天,C(FS,无滞后)最早开始第 6 天;A 的最早完成是第 5 天。A 的自由浮动是多少?
A project manager is calculating free float for a task. Task A (duration 5 days) has two successors: Task B (FS, 0 lag) with an Early Start of day 8 and Task C (FS, 0 lag) with an Early Start of day 6. Task A's Early Finish is day 5. What is Task A's free float?
选项
- A.3 days
- B.0 days
- C.1 day
- D.2 days
解析
解析:C 正确。自由浮动 = 所有紧后任务中最早的最早开始 − 本任务最早完成 = 6 − 5 = 1 天。自由浮动取“最早的紧后任务”(即约束最强者),此处是第 6 天的任务 C。A 若延误超过 1 天就会拖累 C,因此自由浮动为 1 天。总浮动则是对照最晚允许完成时间衡量。
Rationale:C is correct. Free float = earliest Early Start among all immediate successors − Early Finish of the task = 6 − 5 = 1 day. Free float uses the EARLIEST successor, i.e. the most constraining one: here Task C at day 6. If Task A is delayed by more than 1 day it would delay Task C, so free float is 1 day. Total float would instead be measured against the latest allowable finish.
同考点练习题
-
PMP202611-048 · 答案 B
-
PMP202611-060 · 答案 B
-
PMP202611-264 · 答案 A
-
PMP202611-306 · 答案 B
-
PMP202611-430 · 答案 B
-
PMP202611-464 · 答案 D
-
PMP202611-476 · 答案 A
-
PMP202611-664 · 答案 B