关键路径与浮动时间 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-391

题目

项目经理计算某任务自由浮动:任务 A 工期 5 天,有两个紧后任务——B(FS,无滞后)最早开始第 8 天,C(FS,无滞后)最早开始第 6 天;A 的最早完成是第 5 天。A 的自由浮动是多少?
A project manager is calculating free float for a task. Task A (duration 5 days) has two successors: Task B (FS, 0 lag) with an Early Start of day 8 and Task C (FS, 0 lag) with an Early Start of day 6. Task A's Early Finish is day 5. What is Task A's free float?

选项

  1. A.3 days
  2. B.0 days
  3. C.1 day
  4. D.2 days
正确答案:C

解析

解析:C 正确。自由浮动 = 所有紧后任务中最早的最早开始 − 本任务最早完成 = 6 − 5 = 1 天。自由浮动取“最早的紧后任务”(即约束最强者),此处是第 6 天的任务 C。A 若延误超过 1 天就会拖累 C,因此自由浮动为 1 天。总浮动则是对照最晚允许完成时间衡量。 Rationale:C is correct. Free float = earliest Early Start among all immediate successors − Early Finish of the task = 6 − 5 = 1 day. Free float uses the EARLIEST successor, i.e. the most constraining one: here Task C at day 6. If Task A is delayed by more than 1 day it would delay Task C, so free float is 1 day. Total float would instead be measured against the latest allowable finish.