关键路径与浮动时间 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-430

题目

网络图中有三条路径:A→C→E 共 14 天,A→B→D→E 共 16 天,A→B→F 共 12 天。哪条是关键路径,项目工期多少?
A project has the following activities on its network diagram: A→C→E (total 14 days), A→B→D→E (total 16 days), A→B→F (total 12 days). Which path is critical and what is the project duration?
网络图中有三条路径:A→C→E 共 14 天,A→B→D→E 共 16 天,A→B→F 共 12 天。哪条是关键路径,项…

选项

  1. A.Path A→C→E, 14 days
  2. B.Path A→B→D→E, 16 days
  3. C.Path A→B→F, 12 days
  4. D.All three paths are critical
正确答案:B

解析

解析:B 正确。关键路径是网络中最长的路径,决定项目最短工期。A→B→D→E 共 16 天为最长,即关键路径,项目工期 16 天。A→C→E 浮动 2 天(16−14),A→B→F 浮动 4 天(16−12)。16 天路径上任一活动延误都会推后完工日期。 Rationale:B is correct. The critical path is the longest path through the network and determines the minimum project duration. A→B→D→E at 16 days is the longest, so it is the critical path and the project duration is 16 days. A→C→E has 2 days of float (16−14). A→B→F has 4 days of float (16−12). Any delay on the 16-day path delays the project end date.