知识管理与经验 中等 Business Environment 商业环境域 题号 PMP202611-661

题目

项目结束时召开经验教训会议的首要收益是什么?
What is the PRIMARY benefit of conducting a lessons learned session at the end of a project?

选项

  1. A.To assign blame for project failures
  2. B.To capture knowledge for organizational process assets and future project improvement
  3. C.To celebrate project success with stakeholders
  4. D.To fulfill audit requirements
正确答案:B

解析

解析:经验教训把成功与失败沉淀为组织过程资产,用以改善未来绩效;会议应“不追责”。 Rationale:Lessons learned capture successes and failures that become organizational process assets, improving future performance; the session must be blameless.