题目
项目结束时召开经验教训会议的首要收益是什么?
What is the PRIMARY benefit of conducting a lessons learned session at the end of a project?
选项
- A.To assign blame for project failures
- B.To capture knowledge for organizational process assets and future project improvement
- C.To celebrate project success with stakeholders
- D.To fulfill audit requirements
解析
解析:经验教训把成功与失败沉淀为组织过程资产,用以改善未来绩效;会议应“不追责”。
Rationale:Lessons learned capture successes and failures that become organizational process assets, improving future performance; the session must be blameless.
同考点练习题
-
PMP202611-015 · 答案 B
-
PMP202611-023 · 答案 B
-
PMP202611-132 · 答案 B
-
PMP202611-154 · 答案 B
-
PMP202611-181 · 答案 B
-
PMP202611-275 · 答案 A
-
PMP202611-328 · 答案 C
-
PMP202611-382 · 答案 A