项目经理有一名成员拥有无人可替代的独特技能,形成单点故障风险。项目经理应主动做什么?
A project manager has a team member with unique skills that no one else possesses. This creates a single point of failure risk. What should the project manager do proactively?
选项
- A.Implement knowledge transfer: cross-train at least one other team member, create documentation of key processes, and identify a backup resource: converting a risk into a managed situation.
- B.Document the risk in the risk register and monitor it.
- C.Hire a second specialist immediately to eliminate the single point of failure.
- D.Retain the specialist at premium compensation to prevent their departure.
解析
解析:A 正确。知识转移与交叉培训是应对单点故障型资源风险的标准主动措施:成本可控、增强团队能力,且无需立刻增加人头。只做文档(B)只记录风险而不缓解;立刻再招(C)未必有预算或必要;高薪留人(D)只应对离职风险,应对不了病假、休假或突发缺勤。
Rationale:A is correct. Knowledge transfer and cross-training is the standard proactive response to single-point-of-failure resource risk. It is cost-effective, builds team capability and reduces dependency without requiring immediate additional headcount. Documentation only (B) doesn't mitigate the risk. It only records it. Immediate second hire (C) may not be budgeted or justified. Retention compensation (D) addresses departure risk but not absence due to illness, vacation or unexpected leave.