项目经理发现某成员不具备所分配任务所需技能,应当怎么做?
A project manager discovers that a team member lacks the necessary skills for an assigned task. What should the PM do?
选项
- A.Reassign the task to a more skilled team member
- B.Identify training needs and implement a development plan
- C.Remove the team member from the project
- D.Complete the task personally
解析
解析:管理团队包含能力建设:先识别技能差距,再提供培训、辅导等发展机会,同时也能提升士气。
Rationale:Managing the team includes developing competencies: identify the skill gap, then provide training, mentoring or other development, which also builds morale.