题目
一位资深工程师将在两个月后退休。她是唯一了解遗留计费接口如何运作的人,而你的项目下个季度必须与该接口对接。最佳做法是什么?
A senior engineer will retire in two months. She is the only person who understands how the legacy billing interface works, and your project must connect to it next quarter. What is the best course of action?
选项
- A.Ask her to work overtime to finish all interface work before she leaves.
- B.Plan knowledge transfer now: pair her with team members and record the key knowledge.
- C.Hire a contractor after she retires.
- D.Note the concern in the risk register and act after she leaves.
解析
解析:考纲要求识别对项目至关重要的知识,加以收集,并营造便于转移的环境。现在行动的成本远低于事后补窟窿;靠加班也只是拖延,最终仍无人掌握该接口。
Rationale:The ECO asks you to identify knowledge critical to the project, gather it, and create an environment for transfer. Acting now costs far less than fixing the gap later. Overtime still leaves no one who knows the interface.