某 Scrum 团队已良好协作 6 个月,一名高绩效成员宣布离职。团队担心知识流失与士气受影响。Scrum Master 应优先做什么?
A Scrum team has been working well together for 6 months. A high-performing member announces they are leaving the company. The team is concerned about knowledge loss and morale. What should the Scrum Master prioritise?
选项
- A.Facilitate knowledge transfer sessions, pair the departing member with others, address team morale openly in the retrospective, and plan for the transition period.
- B.Reassign the departing member's tasks to the strongest remaining team member.
- C.Immediately hire a replacement to maintain team velocity.
- D.Tell the team that velocity may drop temporarily and continue as normal.
解析
解析:A 正确。知识转移、士气管理与过渡规划,正好覆盖人员离职的三方面影响:知识风险、团队动态与连续性。立即招聘(C)解决不了知识转移与情绪;把任务压给一个人(B)造成瓶颈与超载;只接受速率下降(D)过于被动,错失减轻冲击的机会。
Rationale:A is correct. Knowledge transfer, morale management and transition planning address all three dimensions of the departure: knowledge risk, team dynamics and continuity. Immediate hiring (C) doesn't address knowledge transfer or morale. Reassigning to one person (B) creates a bottleneck and risks overloading them. Simply accepting the velocity drop (D) is passive and misses the opportunity to mitigate impact.