经验教训与知识管理 · PMP 练习题解析

知识管理与经验 中等 Business Environment 商业环境域 题号 PMP202611-023

题目

你的项目即将收尾。在最终的经验教训会议上,团队发现同一类供应商交付延误已影响了过去三个项目。你应该怎么做?
Your project is closing. During the final lessons learned session, the team finds that the same vendor delivery delays have hit three past projects. What should you do?

选项

  1. A.Record the lesson in the lessons learned register and close the project.
  2. B.Record the lesson and work with the PMO to update organizational process assets, such as the vendor selection checklist.
  3. C.Name the procurement team as the cause in the final report.
  4. D.Take no action because the project is already closing.
正确答案:B

解析

解析:收尾包含最终经验教训总结。只有改变未来项目的做法,经验教训才能产生改进;考纲称之为更新组织过程资产。问责不能修复流程。 Rationale:Closure includes final lessons learned. A lesson only creates improvement when it changes how future projects work. The ECO calls this updating your organization’s process assets, and it is how teams keep getting better. Blame does not fix the process.