题目
项目接近完工,项目经理正准备最终的经验教训总结。一名资深成员说“没时间搞这个,直接收尾往前走吧”。项目经理应该怎么做?
A project is approaching completion. The project manager is preparing the final lessons learned. A senior team member says "we don't have time for this: let's just close out and move on." What should the project manager do?
选项
- A.Skip the lessons learned to accommodate the team's priorities.
- B.Conduct a brief 15-minute lessons learned to satisfy the requirement without meaningful discussion.
- C.Conduct the lessons learned. It is a required closure activity. Explain its value for future projects and the team's own careers, and keep the session focused and time-bounded.
- D.Write the lessons learned yourself based on your own observations without team input.
解析
解析:C 正确。经验教训总结是 PMBOK 要求的收尾活动,也是组织学习的基础环节。项目经理应认真组织,同时回应成员顾虑——把会议做聚焦、控时长,并说明其价值。跳过(A)违反收尾要求;独自撰写(D)丢掉了最有价值的视角;形式主义的 15 分钟打勾(B)既不符合初衷也产生不了价值。
Rationale:C is correct. Lessons learned is a required project closure activity in PMBOK and a fundamental component of organisational learning. The PM should conduct it properly, address the team member's concern by keeping it focused and time-efficient, and explain its value. Skipping it (A) violates closure requirements. Doing it alone without team input (D) loses the most valuable perspectives. A performative 15-minute box-tick (B) satisfies neither the intent nor the value of the activity.