题目
一位掌握遗留系统关键知识的资深工程师将在两周后离职。你应该怎么做?
A senior engineer who holds key knowledge about a legacy system will leave the company in two weeks. What should you do?
选项
- A.Ask HR to delay the exit.
- B.Plan knowledge transfer now through pairing, recorded walkthroughs and documentation.
- C.Hire a replacement after the engineer leaves.
- D.Remove the legacy work from the scope.
解析
解析:主动的知识转移能降低关键知识流失风险。结对与文档能把知识扩散到整个团队;等到人走了再处理就会留下能力断层。
Rationale:Proactive knowledge transfer reduces the risk of losing critical knowledge. Pairing and documentation spread knowledge across the team; waiting until after the exit creates a gap.