经验教训与知识管理 · PMP 练习题解析

知识管理与经验 中等 Business Environment 商业环境域 题号 PMP202611-132

题目

完成一次重大产品发布项目后,项目经理组织了全面的经验教训总结。多位参与者指出一些反复出现的流程问题,已影响组织内多个项目而非仅此一个。项目经理应如何处理这些发现?
After completing a major product launch project, the project manager conducts a comprehensive lessons learned session. Several participants identify recurring process issues that have affected multiple projects across the organization, not just this one. What should the project manager do with these findings?

选项

  1. A.Document them in this project's final report and close the project
  2. B.Share the findings with the PMO for integration into organizational process assets and recommend specific process improvements
  3. C.Email the findings to other project managers as a courtesy reference
  4. D.Present the findings at the next department meeting for general awareness
正确答案:B

解析

解析:具备组织级影响的教训应上报 PMO,纳入组织过程资产,使知识驱动跨项目的持续改进。非正式分享(邮件、会议)缺乏系统改进所需的结构化机制。 Rationale:Lessons learned with organization-wide implications should be escalated to the PMO for integration into organizational process assets, ensuring the knowledge drives continuous improvement across projects. Informal sharing lacks the structure needed for systematic improvement.