项目第一阶段刚刚结束,暴露出若干问题,第二阶段下周启动。你现在应该做什么?
Phase one of your project just finished with several problems. Phase two starts next week. What should you do now?
选项
- A.Wait until the project ends to collect lessons learned.
- B.Capture lessons learned now and use them to adjust plans for phase two.
- C.Start phase two as planned.
- D.Ask the team to forget phase one.
解析
解析:经验教训应在项目全过程持续收集。立即应用能避免下一阶段重犯同样的错误。
Rationale:Lessons learned should be captured throughout the project. Using them immediately prevents repeating the same mistakes in the next phase.