相关方分析与权力利益方格 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-662

题目

某相关方权力高、利益低。按权力/利益方格,项目经理应如何管理?
A stakeholder has high power but low interest. According to the Power/Interest Grid, how should the PM manage this stakeholder?

选项

  1. A.Monitor with minimal effort
  2. B.Keep satisfied with regular communication
  3. C.Manage closely and keep informed
  4. D.Keep informed with general updates
正确答案:B

解析

解析:高权力低利益应对策略是“使其满意”:沟通足够维持支持,但不过度打扰;高权力高利益才需要“密切管理”。 Rationale:High power + low interest = keep satisfied: enough communication to maintain support without overwhelming them. High power + high interest = manage closely.