敏捷与混合实践 困难 Process 过程域 题号 PMP202611-655

题目

项目经理采用敏捷方式。哪一项仪式专门用于团队过程的持续改进?
A project manager is using an Agile approach. Which ceremony focuses on continuous improvement of the team's process?

选项

  1. A.Daily standup
  2. B.Sprint planning
  3. C.Sprint review
  4. D.Sprint retrospective
正确答案:D

解析

解析:回顾会专门用于团队反思与过程改进:哪些做得好、哪些不好、下个迭代可采取哪些改进动作。 Rationale:The retrospective is dedicated to team reflection and process improvement: what went well, what did not, and actionable improvements for the next sprint.