敏捷估算与故事点 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-654

题目

某敏捷团队完成十二轮迭代后,Scrum Master 得知市场将出现一项新技术。团队对其了解很少,担心会让计划中的产品过时。最佳做法是:
An agile team has completed twelve iterations when the Scrum Master learns of new technology coming to market. With little understanding of it, the team worries it may render the planned product obsolete. What is the best course of action?

选项

  1. A.Schedule a spike
  2. B.Terminate the project
  3. C.Continue working as planned
  4. D.Update the lessons learned register
正确答案:A

解析

解析:探针是一段有时间盒的短周期研究,用于弄清问题或新技术的实质与影响;先搞明白,才能判断是转向还是继续。 Rationale:A spike is a short, timeboxed investigation to understand an issue or new technology and its impact — necessary before deciding to pivot or continue.

同考点练习题