敏捷与混合实践 中等 Process 过程域 题号 PMP202611-157

题目

一次发布在生产环境失败,团队士气低落,部分成员开始相互指责。你应该怎么做?
A release failed in production, and the team feels demotivated. Some members are blaming each other. What should you do?

选项

  1. A.Find the person responsible and document it.
  2. B.Hold a blameless retrospective focused on learning and improvement actions.
  3. C.Skip the retrospective to save time for fixes.
  4. D.Ask the sponsor to speak to the team.
正确答案:B

解析

解析:不追责的回顾会能让团队学习、重建信任并达成改进措施。追责会让人以后隐瞒问题;跳过反思则可能重蹈覆辙。 Rationale:A blameless retrospective helps the team learn, rebuild trust and agree improvements. Blame makes people hide problems in future; skipping reflection risks repeating the failure.