题目
回顾会上,一名成员说“回顾会纯属浪费时间,什么都没改变”,另有几人点头附和。Scrum Master 应该怎么做?
During a retrospective, a team member says "retrospectives are a waste of time: nothing ever changes." Several others nod in agreement. What should the Scrum Master do?
选项
- A.Cancel retrospectives temporarily and reintroduce them when the team is more receptive.
- B.Ask the team to vote on whether to continue holding retrospectives.
- C.Defend the value of retrospectives by explaining the Scrum framework principles.
- D.Acknowledge the team's frustration, review previous retrospective action items to identify what was and was not implemented, and co-create a more accountable follow-through process.
解析
解析:D 正确。这条抱怨本身是有效反馈:行动项不落地,回顾会自然失去价值。Scrum Master 应认可这种感受,审计以往行动项的去向,并建立更好的问责机制(指定负责人、在下一冲刺跟踪)。空谈理论(C)等于否定真实体验;取消回顾(A)拆掉关键改进机制;投票决定 Scrum 仪式(B)并非 Scrum 的治理方式。
Rationale:D is correct. The complaint is valid feedback: if action items are not followed through, retrospectives lose value. The Scrum Master should acknowledge the concern, audit what happened to past actions, and build a better accountability mechanism (assigning owners, tracking in the next sprint). Defending theory (C) dismisses real experience. Cancelling (A) removes a critical improvement mechanism. Voting on Scrum ceremonies (B) is not how Scrum governance works.