在冲刺回顾会上,团队发现每日站会因会中展开问题解决讨论而耗时 45 分钟,而非预期的 15 分钟。最恰当的做法是什么?
At the sprint retrospective, the team identifies that the daily standup is taking 45 minutes instead of 15 due to problem-solving discussions during the meeting. What is the most appropriate action?
选项
- A.Cancel the daily standup and replace it with a written status update tool.
- B.Assign a timekeeper to cut off any discussion after 15 minutes regardless of content.
- C.Extend the daily standup to one hour to accommodate the team's discussion needs.
- D.Limit the standup to three questions and move problem-solving discussions to immediately after for only those involved.
解析
解析:D 正确。每日站会的目的是同步,而非解决问题。Scrum 指南明确:站会回答三个问题(我做了什么、将做什么、有什么阻碍),问题解决应放在会后由相关人专项讨论。取消站会(A)丢掉有价值的仪式;延长会(C)把失调制度化;硬性限时(B)可能让阻碍问题悬而未决。
Rationale:D is correct. The daily standup's purpose is synchronisation, not problem-solving. The Scrum Guide is explicit: the standup answers three questions (What did I do? What will I do? What is blocking me?) and problem-solving happens in separate, focused discussions with relevant parties. Cancelling it (A) removes a valuable ceremony. Extending it (C) formalises the dysfunction. An arbitrary cut-off (B) may leave blocking issues unresolved.