Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-253

题目

在冲刺回顾会上,团队发现每日站会因会中展开问题解决讨论而耗时 45 分钟,而非预期的 15 分钟。最恰当的做法是什么?
At the sprint retrospective, the team identifies that the daily standup is taking 45 minutes instead of 15 due to problem-solving discussions during the meeting. What is the most appropriate action?

选项

  1. A.Cancel the daily standup and replace it with a written status update tool.
  2. B.Assign a timekeeper to cut off any discussion after 15 minutes regardless of content.
  3. C.Extend the daily standup to one hour to accommodate the team's discussion needs.
  4. D.Limit the standup to three questions and move problem-solving discussions to immediately after for only those involved.
正确答案:D

解析

解析:D 正确。每日站会的目的是同步,而非解决问题。Scrum 指南明确:站会回答三个问题(我做了什么、将做什么、有什么阻碍),问题解决应放在会后由相关人专项讨论。取消站会(A)丢掉有价值的仪式;延长会(C)把失调制度化;硬性限时(B)可能让阻碍问题悬而未决。 Rationale:D is correct. The daily standup's purpose is synchronisation, not problem-solving. The Scrum Guide is explicit: the standup answers three questions (What did I do? What will I do? What is blocking me?) and problem-solving happens in separate, focused discussions with relevant parties. Cancelling it (A) removes a valuable ceremony. Extending it (C) formalises the dysfunction. An arbitrary cut-off (B) may leave blocking issues unresolved.