整合管理 中等 Process 过程域 题号 PMP202611-656

题目

项目最重要的特征是什么?
What is the MOST important characteristic of a project?

选项

  1. A.It has a defined budget
  2. B.It is temporary with a definite beginning and end
  3. C.It requires a large team
  4. D.It must use waterfall methodology
正确答案:B

解析

解析:项目是为创造独特产品、服务或成果而进行的临时性工作;“临时性”正是项目区别于日常运营的关键。 Rationale:A project is a temporary endeavor undertaken to create a unique product, service or result; the temporary nature is what distinguishes it from ongoing operations.