Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-278

题目

产品负责人在每个冲刺开始时不断调整优先级,导致团队反复结转未完成工作,士气下滑。Scrum Master 应该怎么做?
The Product Owner keeps changing priorities at the start of each sprint, causing the team to carry over incomplete work repeatedly. Team morale is dropping. What should the Scrum Master do?

选项

  1. A.Educate the Product Owner on the cost of mid-sprint changes, enforce sprint goal stability during the sprint, and work with the PO to improve backlog readiness before sprint planning.
  2. B.Tell the Product Owner they are not allowed to change priorities once a sprint has started.
  3. C.Allow the PO to change priorities freely: flexibility is a core agile value.
  4. D.Raise the issue with the PO's manager to enforce discipline.
正确答案:A

解析

解析:A 正确。Scrum Master 的职责是在冲刺中保护团队,并辅导产品负责人做好待办管理。让其理解不稳定的真实代价(速率下降、士气受损),并在计划前打磨待办,才能治本。一概禁止(B)夸大了 Scrum Master 的权限;无限制灵活(C)无视冲刺承诺的意义;直接上报(D)跳过辅导。 Rationale:A is correct. The Scrum Master's role is to protect the team during the sprint and coach the PO on effective backlog management. Educating the PO on the real cost of instability (reduced velocity, morale damage) and improving pre-sprint refinement prevents the root cause. Blanket prohibition (B) overstates the Scrum Master's authority. Unlimited flexibility (C) ignores the sprint commitment's purpose. Escalating immediately (D) skips the coaching step.

同考点练习题