Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-257

题目

在待办事项梳理中,产品负责人于冲刺中途向冲刺待办加入一个高优先级故事,称其为客户演示所急需。团队的冲刺承诺将受影响。应该如何处理?
During backlog refinement, the Product Owner adds a new high-priority story to the sprint backlog mid-sprint, claiming it is urgent for a client demo. The team's sprint commitment would be affected. What should happen?

选项

  1. A.The Scrum Master should reject the story and tell the PO it violates Scrum rules.
  2. B.The development team should decide whether to accept or reject the new story without PO involvement.
  3. C.The Product Owner and team should negotiate: either the new story replaces a lower-priority committed story, or it waits for the next sprint.
  4. D.The team should accept the new story and work overtime to complete both the original and new commitments.
正确答案:C

解析

解析:C 正确。在 Scrum 中,冲刺待办归开发团队所有,但可以协商变更。若团队同意移除等量的工作,产品负责人就可以加入新故事,从而维持冲刺承诺,兼顾灵活性与可预测性。加班(D)治标不治本;一概拒绝(A)无视产品负责人的优先级权限;团队抛开产品负责人自决(B)破坏了其问责角色。 Rationale:C is correct. In Scrum, the sprint backlog belongs to the development team, but changes can be negotiated. The PO can add a story if the team agrees to remove something of equal size: maintaining the sprint commitment. This preserves both flexibility and predictability. Overtime (D) treats symptoms not the process. A blanket rejection (A) ignores the PO's authority to reprioritise. The team deciding without PO (B) removes the PO from their accountability.