题目
在待办事项梳理中,产品负责人于冲刺中途向冲刺待办加入一个高优先级故事,称其为客户演示所急需。团队的冲刺承诺将受影响。应该如何处理?
During backlog refinement, the Product Owner adds a new high-priority story to the sprint backlog mid-sprint, claiming it is urgent for a client demo. The team's sprint commitment would be affected. What should happen?
选项
- A.The Scrum Master should reject the story and tell the PO it violates Scrum rules.
- B.The development team should decide whether to accept or reject the new story without PO involvement.
- C.The Product Owner and team should negotiate: either the new story replaces a lower-priority committed story, or it waits for the next sprint.
- D.The team should accept the new story and work overtime to complete both the original and new commitments.
解析
解析:C 正确。在 Scrum 中,冲刺待办归开发团队所有,但可以协商变更。若团队同意移除等量的工作,产品负责人就可以加入新故事,从而维持冲刺承诺,兼顾灵活性与可预测性。加班(D)治标不治本;一概拒绝(A)无视产品负责人的优先级权限;团队抛开产品负责人自决(B)破坏了其问责角色。
Rationale:C is correct. In Scrum, the sprint backlog belongs to the development team, but changes can be negotiated. The PO can add a story if the team agrees to remove something of equal size: maintaining the sprint commitment. This preserves both flexibility and predictability. Overtime (D) treats symptoms not the process. A blanket rejection (A) ignores the PO's authority to reprioritise. The team deciding without PO (B) removes the PO from their accountability.