Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-008

题目

图示为一个 10 天迭代的第 6 天(承诺 80 个故事点):实际剩余 64 点,而理想线应为 32 点。项目经应该怎么做?
The chart shows day 6 of a 10-day iteration with 80 story points committed: 64 points remain versus an ideal of 32. What should the project manager do?
图示为一个 10 天迭代的第 6 天(承诺 80 个故事点):实际剩余 64 点,而理想线应为 32 点。项目经应该怎么…

选项

  1. A.Add two developers to the team today.
  2. B.Raise the trend with the team, look for impediments, and talk with the product owner about the iteration scope.
  3. C.Extend the iteration by five days.
  4. D.Report to the sponsor that the iteration has failed.
正确答案:B

解析

解析:理想线显示应剩 32 点,实际剩 64 点,说明迭代进度落后。服务型领导应帮助团队发现并清除障碍,并让产品负责人参与范围取舍。中途加人通常无益,固定迭代周期也不应随意延长。 Rationale:The team has 64 points left when the ideal line shows 32, so the iteration is behind. A servant leader helps the team find and remove blockers and involves the product owner in any scope trade-off. Adding people late rarely helps, and fixed iteration lengths should not stretch.

同考点练习题