图示为一个 10 天迭代的第 6 天(承诺 80 个故事点):实际剩余 64 点,而理想线应为 32 点。项目经应该怎么做?
The chart shows day 6 of a 10-day iteration with 80 story points committed: 64 points remain versus an ideal of 32. What should the project manager do?
选项
- A.Add two developers to the team today.
- B.Raise the trend with the team, look for impediments, and talk with the product owner about the iteration scope.
- C.Extend the iteration by five days.
- D.Report to the sponsor that the iteration has failed.
解析
解析:理想线显示应剩 32 点,实际剩 64 点,说明迭代进度落后。服务型领导应帮助团队发现并清除障碍,并让产品负责人参与范围取舍。中途加人通常无益,固定迭代周期也不应随意延长。
Rationale:The team has 64 points left when the ideal line shows 32, so the iteration is behind. A servant leader helps the team find and remove blockers and involves the product owner in any scope trade-off. Adding people late rarely helps, and fixed iteration lengths should not stretch.