Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-303

题目

某 Scrum 团队刚完成冲刺计划,冲刺待办包含 30 个故事点。第 3 天,此前交付的软件被发现一个严重生产缺陷。团队应该怎么做?
A Scrum team has just completed sprint planning. The sprint backlog contains 30 story points. On day 3, a critical production bug is discovered in previously delivered software. What should the team do?

选项

  1. A.Work overtime to fix the bug AND complete all sprint backlog items.
  2. B.Ignore the bug until the next sprint: changes to sprint backlog are not allowed after planning.
  3. C.Ask a separate operations team to fix the bug so the development team can complete the sprint.
  4. D.The team should address the critical production bug immediately. If significant effort is required, the Scrum Master and PO should negotiate removing lower-priority stories from the current sprint to maintain a sustainable pace.
正确答案:D

解析

解析:D 正确。严重生产缺陷属于必须处理的计划外工作,是一种障碍。Scrum 的正确应对是透明处理:先修缺陷,再与产品负责人协商冲刺范围以维持可持续节奏,冲刺目标可能需相应调整。放任生产缺陷(B)在实践中不可接受;完全交给运维(C)也许可行,但开发团队仍要对自家软件负责;靠加班硬扛(A)违反可持续节奏。 Rationale:D is correct. Critical production bugs represent unplanned work that must be addressed. They are a form of impediment. The correct Scrum response is to handle it transparently: fix the bug, then negotiate sprint scope with the PO to maintain a sustainable pace. The sprint goal may need to be adjusted. Ignoring a production bug (B) is unacceptable in practice. Separate ops team (C) may work but the development team remains responsible for their software. Overtime (A) violates sustainable pace.