题目
某 Scrum 团队刚完成冲刺计划,冲刺待办包含 30 个故事点。第 3 天,此前交付的软件被发现一个严重生产缺陷。团队应该怎么做?
A Scrum team has just completed sprint planning. The sprint backlog contains 30 story points. On day 3, a critical production bug is discovered in previously delivered software. What should the team do?
选项
- A.Work overtime to fix the bug AND complete all sprint backlog items.
- B.Ignore the bug until the next sprint: changes to sprint backlog are not allowed after planning.
- C.Ask a separate operations team to fix the bug so the development team can complete the sprint.
- D.The team should address the critical production bug immediately. If significant effort is required, the Scrum Master and PO should negotiate removing lower-priority stories from the current sprint to maintain a sustainable pace.
解析
解析:D 正确。严重生产缺陷属于必须处理的计划外工作,是一种障碍。Scrum 的正确应对是透明处理:先修缺陷,再与产品负责人协商冲刺范围以维持可持续节奏,冲刺目标可能需相应调整。放任生产缺陷(B)在实践中不可接受;完全交给运维(C)也许可行,但开发团队仍要对自家软件负责;靠加班硬扛(A)违反可持续节奏。
Rationale:D is correct. Critical production bugs represent unplanned work that must be addressed. They are a form of impediment. The correct Scrum response is to handle it transparently: fix the bug, then negotiate sprint scope with the PO to maintain a sustainable pace. The sprint goal may need to be adjusted. Ignoring a production bug (B) is unacceptable in practice. Separate ops team (C) may work but the development team remains responsible for their software. Overtime (A) violates sustainable pace.