Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-184

题目

冲刺燃尽图前四天平稳下降,随后三天变成一条水平线。这最可能说明什么,应该怎么做?
A sprint burndown chart shows a steady downward line for the first four days, then a flat line for the next three days. What does this most likely mean, and what should happen?
冲刺燃尽图前四天平稳下降,随后三天变成一条水平线。这最可能说明什么,应该怎么做?

选项

  1. A.The team finished early; close the sprint.
  2. B.Work has stalled, possibly due to blockers; raise it at the daily stand-up to find and remove impediments.
  3. C.The chart is wrong; stop using it.
  4. D.Add more work to the sprint.
正确答案:B

解析

解析:燃尽图走平说明剩余工作没有减少。团队应在站会上查明原因并清除障碍;忽视这一信号可能导致冲刺目标落空。 Rationale:A flat burndown means remaining work is not decreasing. The team should identify why at the stand-up and remove the blockers; ignoring the signal risks missing the sprint goal.