团队在实施 AI 客服机器人:数据科学关注模型准确率,合规关注风险规避,客服关注降低来电量。决策看起来前后不一,项目目标也显得模糊。为推动共同愿景,项目经理下一步最该做什么?
A team is implementing an AI customer-support chatbot. Data Science optimizes model accuracy, Compliance optimizes risk avoidance, Customer Service optimizes call volume reduction. Decisions seem inconsistent and the project's purpose feels unclear. What should the PM do next to best promote a shared vision?
选项
- A.Facilitate a working session with key stakeholders and the team to align on a concise AI product vision and shared success criteria, then connect near-term backlog priorities to that vision.
- B.Work with each function to define measurable success metrics aligned to its objectives and create a balanced scorecard to monitor performance across model quality, risk controls, and operational efficiency.
- C.Ask the project sponsor to clarify the primary strategic objective for the chatbot so the team can prioritize decisions consistently
- D.Establish a governance process that requires proposed changes to model behavior or compliance rules to be reviewed by representatives from all three functions before implementation.
解析
解析:根因是缺少共同愿景与统一的成功标准,各方都在局部最优。先促成对齐,之后的度量、治理与优先级排序才有共同基准。
Rationale:The root issue is absence of a shared vision and unified success criteria; each group optimizes locally. Facilitating alignment first lets metrics, governance and prioritization work consistently afterwards.