题目
你所在敏捷团队的速率已连续四个冲刺上升,但客户表示产品仍未解决他们的问题。你应该怎么做?
Your agile team's velocity has risen for four sprints, but the customer says the product still does not solve their problem. What should you do?
选项
- A.Celebrate the higher velocity.
- B.Work with the product owner and customer to review outcomes and reorder the backlog by value.
- C.Ask the team to work faster.
- D.Add more features.
解析
解析:速率衡量的是产出而非价值。与客户复盘成果并按价值重排优先级,才能让团队聚焦解决真问题。
Rationale:Velocity measures output, not value. Reviewing outcomes with the customer and reordering by value focuses the team on solving the real problem.