敏捷与混合实践 中等 Process 过程域 题号 PMP202611-011

题目

你的混合项目正在替换旧的订单系统。在冲刺评审会上,销售团队把目标描述为“更快报价”,仓库团队则描述为“更少发货错误”。团队不断开发方向相互拉扯的功能。你首先应该做什么?
Your hybrid project is replacing an old order system. In sprint reviews, the sales team describes the goal as faster quotes, while the warehouse team describes it as fewer shipping errors. The team keeps building features that pull in different directions. What should you do first?

选项

  1. A.Ask the sponsor to send a memo that picks one goal.
  2. B.Facilitate a session with key stakeholders to agree on a shared vision and success measures.
  3. C.Let each department build the features it wants.
  4. D.Freeze the backlog until the two teams stop disagreeing.
正确答案:B

解析

解析:考纲要求项目经理帮助建立共同愿景,并找到误解的根源。备忘录也许能换来服从,但换不来认同;冻结待办会中断价值交付;两边功能都做则是浪费。 Rationale:The ECO asks you to help ensure a shared vision and find the root cause of any misunderstanding. A memo may win compliance but not buy-in. Freezing the backlog stops value, and building both sets of features wastes effort.