题目
你的敏捷团队产品待办列表中有 40 个条目。发起人希望在投入更多资金之前先做一个早期发布,以测试市场需求。最佳做法是什么?
Your agile team has 40 items in the product backlog. The sponsor wants an early release to test market demand before investing more money. What is the best approach?
选项
- A.Deliver all must-have and nice-to-have features in one release.
- B.Work with the product owner to build a minimum viable product (MVP) from the top-value items.
- C.Ask the team to work overtime so all 40 items ship sooner.
- D.Build a detailed work breakdown structure for all 40 items first.
解析
解析:MVP 能够尽早交付价值,并获得真实用户反馈。考纲要求按价值排序工作,并寻找以小步方式交付的途径。
Rationale:An MVP delivers value early and gives real user feedback. The ECO asks you to rank work by value and look for ways to deliver in small steps.
同考点练习题
-
PMP202611-011 · 答案 B
-
PMP202611-078 · 答案 C
-
PMP202611-130 · 答案 B
-
PMP202611-153 · 答案 C
-
PMP202611-182 · 答案 B
-
PMP202611-214 · 答案 A
-
PMP202611-329 · 答案 D
-
PMP202611-352 · 答案 D