整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-648

题目

某制药项目的人体试验进展顺利,CEO 宣布把受试者规模翻倍,并要求用本周上线的新系统跟踪结果。项目经理首先应当做什么?
In a pharmaceutical project, human trials have started successfully. The CEO announces that the patient pool should double and results tracked in a new system launching this week. What should the PM do first?

选项

  1. A.Ramp up production to match the demand of the CEO
  2. B.Consider what might be included in a change request
  3. C.Adjust the scope baseline to reflect the increased trial size
  4. D.Communicate the change in the scope to the project stakeholders
正确答案:B

解析

解析:在实施或通报之前,必须先按项目程序提交变更请求并获批准;因此第一步是把变更请求的内容想清楚。 Rationale:Before any implementation or communication, a change request must be submitted per project procedure and approved; framing the change request comes first.