价值交付与最小可行 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-329

题目

敏捷教练辅导的团队严格照本宣科做 Scrum,但业务成果没有改善。各类仪式按时举行,速率稳定。最可能缺什么?
An agile coach is working with a team that has been doing Scrum by the book but not seeing business results improve. Ceremonies are happening on schedule and velocity is stable. What is likely missing?

选项

  1. A.The team needs to increase velocity to deliver more value.
  2. B.The Product Owner should write better user stories with more detailed acceptance criteria.
  3. C.The sprint length should be shortened to deliver increments faster.
  4. D.The team is doing Scrum mechanically without connecting their work to measurable business outcomes, a focus on business value metrics and outcome-driven backlog prioritisation is needed.
正确答案:D

解析

解析:D 正确。“僵尸 Scrum”——仪式照做但业务无改善——是公认的敏捷反模式,团队关注的是流程合规而非业务成果。解法是把待办事项与可衡量的业务指标挂钩,并确保产品负责人按业务价值而非技术便利排序。低价值工作速率更高(A)只会制造更多浪费;冲刺周期(C)与验收标准(B)相对成果导向都属次要。 Rationale:D is correct. "Zombie Scrum", where ceremonies happen but business results don't improve, is a recognised agile anti-pattern. The team is focused on process compliance rather than business outcomes. The fix is to connect backlog items to measurable business metrics and ensure the PO is prioritising by business value, not just technical convenience. Higher velocity (A) of low-value work produces more waste. Sprint length (C) and acceptance criteria (B) are secondary to outcome focus.

同考点练习题